Resources/Core concepts/Bonds
Bonds
Bond: a three-party guarantee. The principal owes the work or the payment to the obligee, and the surety promises to pay if the principal does not. In Kuhlman, one bond is one record under a project.
A bond is a promise with three parties. The principal owes the work or the payment. The principal owes it to the obligee. The surety guarantees it, and pays if the principal does not. In Kuhlman, one bond is one record, and every bond record nests under a project.
A bond has three seats
| Seat | Who sits there | On a performance bond for a GC |
|---|---|---|
| Principal | The party who owes the work or the payment. | The GC. |
| Obligee | The party the principal owes, who can call the bond. | The owner, or the agency that issued the permit. |
| Surety | The company that guarantees the principal and pays a valid claim. | The surety company that wrote the bond. |
A broker sits beside the bond, not on it. Your bond broker arranges the bond with the surety. Your insurance broker is a different company with a different job; see Insurance. Obligees are owners and agencies. A broker is never an obligee.
Kuhlman tracks eight bond types
| Type | What it guarantees | How it ends |
|---|---|---|
| Bid | You will sign the contract and post the other bonds if you win the bid. | The obligee awards the contract, or you lose the bid. |
| Performance | You will finish the work in the contract. | The obligee releases it after completion, warranty, and claim windows close. |
| Payment | You will pay your subs and suppliers. | The obligee releases it after lien and claim windows close. |
| Warranty | You will fix defects during the warranty period. | The warranty period ends and you have fixed every defect. |
| Maintenance | You will maintain the work for a period after acceptance. | The maintenance period ends. |
| Right of way | You will restore public right of way you disturbed. | The agency accepts the restored right of way. |
| Site improvement | You will complete public improvements a permit requires. | The agency accepts the work. Sometimes a maintenance bond replaces the performance bond. |
| Retainage | You will complete the work, in exchange for the retained cash now. | The obligee pays the retained cash within the statutory window. See below. |
The surety usually issues a performance bond and a payment bond together for the same contract. Kuhlman shows the pair as one line, Performance & Payment, and keeps two records underneath, because each one walks the chain on its own.
A bond moves through one chain of statuses
Standard bonds
- Prep
- Requested from broker
- In review
- Sig ready
- Active
- Release requested
- Released
A Tenant Admin can cancel a bond until it is Released, Forfeited or Expired. If the obligee’s reviewer returns the draft for revision, the bond stays In review.
Retainage bonds
- Prep
- Requested from broker
- In review
- Sig ready
- Active
- Satisfied
No one releases a retainage bond. It reads Satisfied once the obligee pays the retained cash.
| Status | What it means | Who moves it |
|---|---|---|
| Prep | You are assembling the request: type, project, parties, amounts, documents. | You. |
| Requested from broker | You sent the request to your bond broker. The ball is in the broker’s court. | You send. The broker works it. |
| In review | A draft bond form is with the obligee’s reviewer. If they return it for revision, it stays here until you resubmit. | You submit. The obligee reviews. |
| Sig ready | The obligee’s signatory approved the draft. It is ready for you and the surety to sign. | The obligee’s signatory. |
| Active | You uploaded the executed bond. It is in force and counts against capacity. | You upload. We record. |
| Release requested | You asked the obligee to discharge a standard bond. | You. |
| Released | The obligee’s release instrument is on file. The bond is off the books. | We record it when you enter the release letter. |
| Cancelled | A Tenant Admin cancelled the bond before release. | A Tenant Admin, from any status except Released, Forfeited or Expired. |
A standard bond ends by discharge; a retainage bond ends by settlement
A standard bond ends when the obligee lets you off the hook and puts it in writing. The release letter is the evidence, and it dates the event. What has to be true first depends on the type: completion, the warranty period, lien and claim windows, agency acceptance.
A retainage bond ends when money moves. Once the principal posts the bond, the obligee owes the principal the retained cash within a statutory window. When the obligee pays it, the bond reads Satisfied. Under Oregon law the guarantee itself stays in force until the obligee notifies the surety, so Kuhlman records that notice as a separate fact on the bond, not as a status.
Retainage bonds run in both directions
Retainage is the share of each payment the owner holds back until the owner accepts the work. A retainage bond lets the contractor take that cash now. On a GC’s project the bond runs two ways. You post one to the owner, and you are the principal. Your subs post them to you, and you are the obligee. Kuhlman keeps both under the project and shows them on the Sub Contractor Bonds tab, with the cash position they change.
Oregon caps retainage at 5% and requires the cash within 30 days of a compliant bond. Other states differ. Kuhlman never guesses a deadline. We enter each jurisdiction’s cap and window after a legal review, and we use them to set a date only after we ratify them.
Your surety line has a capacity
Your surety gives you a line: the total bonded amount you can have in force. Active exposure is the sum of your active bonds. Pending exposure is the sum of bonds between Prep and Sig ready. Current available is the line minus active exposure. Bonds where you are the obligee, such as a sub’s retainage bond to you, never count against your line. You pay the premium once, up front, usually 1% to 3% of the bond amount, and it rarely renews. To avoid renewal premiums, chase the obligee to release every bond that is ready for release.
You work with bonds on these screens
| Screen | What it shows |
|---|---|
| Bonds | Your construction bonds, grouped by project, with a summary band for capacity, pending and active exposure, open actions, and release-ready bonds. The Sub Contractor Bonds tab shows inbound retainage by project. |
| Bond detail | One bond: parties, ball in court, related huddles, thread, activity timeline, documents, and a closeout checklist. Header actions change with status. |
| Add bond | Five steps: type, project and parties, amounts, documents, review. |
| Record inbound retainage bond | How you record a sub’s retainage bond posted to you. |
We use these terms
- Total bonded amount
- The amount the surety stands behind. Bond forms call it the penal sum.
- Sig ready
- The obligee’s signatory approved it. It now waits for you and the surety to sign.
- Active
- Executed and in force. Counts against your surety line.
- Release requested, Released
- The two steps of discharge on a standard bond. Retainage bonds never use them.
- Satisfied
- The obligee paid the retained cash. The terminal status for a retainage bond.
- Commitment
- A sub’s contract value on the project. On retainage screens, the amount the sub can bond against.
- Max retainage, Retained accepted
- The ceiling on a project’s open retainage program, and the retainage dollars on executed bonds.
- Capacity
- Your surety line, and how much of it is in use.
Read next